ALES a. s., subcontractor of T7 Kemuncak (Malaysia) implements the supply of the ICZ LETVIS ATM (Air Traffic Management) system for the RMAF Kuantan air base.
- In June 2025, as part of the first inspection visit of representatives of RMAF and T7 Kemuncak in Slovakia, we confirmed the readiness of the solution and the schedule of further steps.
- From 17.11. – to 12.12. 2025, intensive training of technicians and operators from Malaysia took place in Liptovský Mikuláš. During 4 weeks, our colleagues trained 2 groups of 15 participants, who successfully passed the theoretical and practical final tests.
- From 23.02. – to 26.02.2026 we have completed internal tests so-called “Factory Acceptance Tests (FAT)” with the active participation of the customer. By signing the resulting FAT documentation and acceptance certificate, the customer confirmed that the finalized product meets the required quality parameters and project requirements.
The result of the FAT tests confirmed the high quality of our ATM system solution. Behind this milestone is the professional and skilled ALES team, which designed the system, prepared detailed testing methodologies and then performed individual tests according to the customer’s requirements.
In addition to the professional part, we also made sure that our partners took away from Slovakia more than just technical knowledge. Our colleagues from Liptovský Mikuláš prepared an interesting leisure program for our business partner.
The next milestone is the shipment of the ATM system and then its on-site installation and integration work in Kuantan. We believe that we will successfully complete the project by the end of 2026.